TOD Project Examples

FacebookTwitterGoogle+Share

Bus TOD Examples

• BTOD Case 1: The Boulder Transit Village (Boulder, Colorado)

• BTOD Case 2: Staples Street Transit Center (Corpus Christi, Texas)

• BTOD Case 3: Noho Arts District (Los Angeles, California)

• BTOD Case 4: Martin Luther King Jr. East Busway (Pittsburgh, Pennsylvania)

• BTOD Case 5: Centre Station/John Deere Commons (Moline, Illinois)

• BTOD Case 6: Uptown District (San Diego, California)

• BTOD Case 7: Aspen Neighborhood (West Davis, California)

• BTOD Case 8: Benjamin and Marian Schuster Performing Arts Center (Dayton, Ohio)

• BTOD Case 9: Adelaide Busway (Adelaide, Australia)

• BTOD Case 10: Brisbane South East Busway (Brisbane, Australia)

• BTOD Case 11: Curitiba BRT (Curitiba, Brazil)

• BTOD Case 12: Ottawa Transitway (Ottawa, Canada)

Rail TOD Examples

• RTOD Case 1: Columbia Pike Streetcar Project (Virginia)

• RTOD Case 2: Rosslyn-Ballston Corridor (Arlington County, Virginia)

• RTOD Case 3: South End TOD (Charlotte, North Carolina)

• RTOD Case 4: Mockingbird Station TOD (Dallas, Texas)

• RTOD Case 5: Englewood CityCenter TOD (Englewood, Colorado)

• RTOD Case 6: Orenco Station Town Center (Hillsboro, Oregon)

• RTOD Case 7: Bethesda Metro Center (Bethesda, Maryland)

• RTOD Case 8: Lindbergh City Center (Atlanta, Georgia)

• RTOD Case 9: Dadeland North and South (Miami, Florida)

• RTOD Case 10: Ohlone-Chynoweth TOD (San Jose, California)

• RTOD Case 11: The Tide – Norfolk’s Future Light Rail Transit System (Norfolk, Virginia)

 

BTOD Case 1
The Boulder Transit Village (Boulder, Colorado)

Project Location Northeast corner of Pearl Pkwy and 30th Street in Boulder, Colorado

BTOD photo

  BTOD photo
Transit Facilities and Services Regional Transportation District (RTD) will develop new transit facilities and services in the area:
• a bus facility near Pearl Parkway and 30th Street, with bus rapid transit (BRT) to Denver along U.S. 36 and enhanced local bus service
• a rail stop at the end of Bluff Street for commuter rail service to Denver and Longmont on existing railroad tracks currently used for freight
TOD Facts • 200-300 or more affordable and market-rate residential housing units
• supportive commercial uses and possibly a park-and-ride lot
Project Participants • Regional Transportation District (RTD)
• City of Boulder
• private sector
Project Phasing A phased approach will be taken for the following components of implementation: the citys funding of key public improvements, the regulatory aspects of the plan involving land use and zoning changes, TDM and transportation connections:
• Phase 1 will occur in the first 10 to 15 years in the area between 30th Street and the railroad tracks.
• Phase 2 will generally occur thereafter and focus on the areas east of the tracks and west of 30th Street.
Project Funding Funds for site selection,concept planning and land purchase were providedby the City of Boulder and RTD. Housing and commercial project elements will likely be financed by a future private developer and private/public partnership. RTD and the City have secured a Federal $7.8 million grant to fund master planning, site planning and design and construction of the first phase regional bus/BRTtransit station. Funding for the future RTD commuter rail transit facilitywill be paidfor by RTD FasTracks.
Lessons Learned • It is unnecessary to wait for a private developer to kick off a TOD project. Government agencies can also take the initiative to start a TOD project.
• Bus transit can also create a successful TOD project. Rail is not the only transit mode for TOD.

Back to top

 

BTOD Case 2
Staples Street Transit Center (Corpus Christi, Texas)

Transit Facilities and Services • The bus transfer station is across the street from City Hall, Corpus Christi, Texas.
• It serves 14 bus routes and some 5,000 daily transit users. The bus transfer facility, built in a Spanish-style motif, features on-site retail offerings and involves public-private equity participation.
  BTOD photo
Exterior of the Staples Street Transit Center

BTOD photo
Interior of the Staples Street Transit Center

TOD Facts • This bus transfer center has become a veritable town square, featuring a weekly farmers market, food concession, and 1,500 tiles hand-painted by local residents and students.
• By all accounts, it has given bus transit a positive image in Corpus Christi.
• The bus transfer center was the recipient of the 1995 Presidential Design Achievement Award.
Project Funding The Corpus Christi RTA and its capital improvements are funded by a 1/2 percent sales tax. A Federal Transit Administration grant of $800,000 was utilized for the completion of the Staples Street Station. FTAs Livable Communities funding is being used for pedestrian improvements to existing transit centers.
Lessons Learned By making people-friendly improvements to such transit centers, it is able to reach beyond the boundaries of building typical bus stops to the larger goal of helping to reshape communities.

Back to top

 

BTOD Case 3
NoHo Arts District (Los Angeles, California)

Project Location North Hollywood in the San Fernando Valley, Los Angeles

BTOD photo

Transit Facilities and Services • Metro Red Line (Heavy Rail)
• Metro Orange Line (BRT)
BTOD photo
TOD Facts • Through the hard work of community stakeholders in partnership with Los Angeles Neighborhood Initiative (LANI) and the Community Redevelopment Agency, NoHo has transformed from a thoroughfare dotted with vacant lots to a burgeoning theater district with coffee shops, restaurants and eclectic retail. In June 2000, the terminal Metro Red Line subway station opened within walking distance of this blossoming neighborhood main street.
• Medium- and high-density developments are being built around the Metro Station.
• Condominium towers (including a 15-story building on Lankershim Blvd) being built in the midst of older one-story bungalows and small apartment complexes.
Project Funding Funding for $100,000 of transit amenities came from a Federal Transit Administrations Livable Communities grant.
Lessons Learned • The NoHo bus TOD reveals more about community development than transit, and illustrates how one of the greatest powers of TOD is to serve as a catalyst to achieve a communitys vision.
• Giving community groups some control over the funds to be used in their neighborhood promoted ongoing public involvement.

Back to top

 

BTOD Case 4
Martin Luther King Jr. East Busway (Pittsburgh, Pennsylvania)

BTOD photo
MLK Busway Route Map
Transit Facilities and Services • The Martin Luther King Jr. East Busway is a two-lane dedicated bus-only highway serving the city of Pittsburgh and many of its eastern neighborhoods and suburbs. Total length is 9.1 miles.
• Three Port Authority routes and other express and suburban Flyer routes utilize the busway seven days a week.
TOD Facts • 59 new developments within 1,500 feet radius of station.
• $302 million in land development benefits of which $275 million was construction. 80% clustered at station.
• New construction and renovation of existing buildings.
• Retail, office and residential uses are most common.

Back to top

 

BTOD Case 5
Centre Station/John Deere Commons (Moline, Illinois)

Project Location Centre Station, 1200 River Drive, Moline, Illinois 61265

BTOD photo

  BTOD photo
Centre Station Photo
Transit Facilities and Services The Centre Station is a bus transfer center developed by the Rock Island County Metropolitan Mass Transit District (MetroLINK) in Illinois. It consists of a 12-bay bus staging area arranged in a sawtooth pattern at the grade level with an elevated bus transfer platform.
TOD Facts The Centre Station in John Deere Commons contains offices, a convention center, a Radisson Hotel, a parking structure, and various pedestrian amenities.
Project Participants

• The Rock Island County Metropolitan Mass Transit District (MetroLINK)
• The United States Department of Transportation, Federal Transit Administration (FTA)
• The Illinois Department of Transportation (IDOT)
• The United States Department of Housing and Urban Development (HUD)
• The Economic Development Administration (EDA)
• Deere & Company

Back to top

 

BTOD Case 6
Uptown District (San Diego, California)

Project Location Uptown District, 1270 Cleveland Avenue, San Diego

BTOD photo

Transit Facilities and Services 6 bus routes (15-minute frequency)
TOD Facts • The Uptown district is a 14-acre mixed-use bus TOD.
• TOD development costs $70 million to develop and consists of 318 housing units, 145,000 square feet of retail and commercial space and a 3,000 square foot community center.
BTOD photo
Uptown District Land Use Map
  BTOD photo
Project Photo
Project Funding The Uptown project was funded by the Citys redevelopment agency ($9 million) and by private companies.
Lessons Learned • With strong city leadership, a bus TOD became an important community asset.
• Uptown is a good example of how to accommodate the needs of the automobile and create a well designed, pedestrian-friendly mixed use TOD.

Back to top

 

BTOD Case 7
Aspen Neighborhood (West Davis, California)

Project Location Corner of Arlington Blvd. and Shasta Drive in West Davis (west of Highway 113), California

BTOD photo

  BTOD photo
A Bus Stop Photo

BTOD photo
A Neighborhood Photo

Transit Facilities and Services 5 bus routes, 5 to 25-minute frequency, and two commuter express routes to downtown Sacramento.
TOD Facts • Aspen Village: includes 88 units on 4.5 acres (at 20 dwelling units per net acre density), with 230 parking spaces (2.6/unit).
• Heather Glen Apartments: consists of 62 units on 3.5 acres (a net density of 17 dwelling units (du)/acre), with 124 parking spaces (2 spaces/unit).
• Muir Commons: consists of 26 self contained townhomes with small yards a large community building with commercial-size kitchen, dining room, childrens playrooms, large meeting room, laundry facilities, a lawn, gardens, childrens play structure, a workshop/garage, an orchard, a hot tub and landscaped sitting areas.
Lessons Learned This neighborhood is a successful example of a suburban bus TOD. There has been very little community opposition to the attractive and well maintained medium-density housing complexes. The private developer has indicated a desire to include transit in future projects due to the benefit of reduced traffic and parking problems in this neighborhood due to its accessibility to high-quality transit service, especially for students.

Back to top

 

BTOD Case 8
Benjamin and Marian Schuster Performing Arts Center (Dayton, Ohio)

Project Location Second and Main streets, Dayton, Ohio

BTOD photo

Transit Facilities and Services Bus services (Routes 1, 2, 4, 7, 11, 14) of the Greater Dayton Regional Transit Authority.
TOD Facts In addition to the Benjamin and Marian Schuster Performing Arts Center, this Bus TOD also has a mix of the following elements:

• Restaurants
• 15-story office tower
• Condominiums
• Garden center (also known as the Winter Garden)
• Penthouse

Project Funding The Schusters have donated $8 million toward the new arts center.
Lessons Learned This is a typical example of urban TOD, which has a great potential to boost bus ridership.

Back to top

 

BTOD Case 9
Adelaide Busway (Adelaide, Australia)

Project Location Adelaide, Australia
BTOD photo
Transit Facilities and Services • At 12 kilometres long, the Adelaide O-Bahn (track-guided bus) is the longest and fastest guided bus service in the world, travelling at speeds up to 100km/hour.
• Currently, there are 22,000 passenger trips daily (8 million a year).
• Adelaide Metro operates the busway.
TOD Facts • In the early 1990s, the site of a new regional college campus was relocated to Tea Tree Gully (busways terminus).
• A medical complex has also sprung up nearby and some degree of clustered, station-area development has occurred.
  BTOD photo
O’Bahn Technology
Lessons Learned Adelaides O-Bahn has proven to be a sensible choice for serving low-density, auto-oriented markets. By blending the speed and safety of light rail transit with the inherent flexibility and efficiencies of bus transit, the O-Bahn system has been successful. Its ridership continues to increase, even though regional transit patronage has fallen.

Back to top

 

BTOD Case 10
Brisbane South East Busway (Brisbane, Australia)

Project Location Brisbane, Australia

BTOD photo

  BTOD photo
Brisbane South East Busway Photo
Transit Facilities and Services • The 17-kilometer (10.5-mile) South East Busway extends from the Brisbane Central Business District to the southern suburb of Eight Mile Plain, adjacent to the South East Freeway. The $400 million-busway includes 10 attractively designed stations and a bus operations center.
• Daily ridership approximates 60,000.
TOD Facts Up to 20% gain in property values near the busway. Property values in area within 6 miles of station grew by 2 to 3 times faster than those at greater distance.

Back to top

 

BTOD Case 11
Curitiba BRT (Curitiba, Brazil)

Project Location Curitiba, Brazil
  BTOD photo
Location of Curitiba, Brazil

BTOD photo
BRT Routes in Curitiba

BTOD photo
BRT Tube Stations in Curitiba

Transit Facilities and Services • Bus rapid transit operates on the five main arterials leading into the center of the city like spokes on a wheel hub.
• Tube stations serve the dual purpose of providing shelter from the elements, and facilitate the simultaneous loading and unloading of passengers.
TOD Facts BRT limited central area growth, while encouraging commercial growth along the transport arteries radiating out from the city center. The city center was partly closed to vehicular traffic, and pedestrian streets were created. Linear development along the arteries reduced the traditional importance of the downtown area.
Lessons Learned • Curitibas BRT successes were due to careful planning, smart decision making, and inspired leadership.
• Curitiba took many innovative measures: the creation of trinary roads, introduction of zoning bonuses, and initiation of direct-line services that tie into boarding tubes.
• Curitiba also kept things simple. Curitiba set off with a small set of realistic long-range goals.

Back to top

 

BTOD Case 12
Ottawa Transitway (Ottawa, Canada)

Project Location Ottawa, Canada
BTOD photo
Ottawa Busway Route Map
Transit Facilities and Services • Using a dedicated busway, Ottawa has achieved many advantages of a rail-based rapid transit system, with an added bonus: vehicles can leave and return to the guideway, thus reducing the need to transfer.
• In 1998, Ottawas bus-only guideway connects more than 200,000 daily passengers to the regions urban centers. Nearly three-quarters of all peak-hour trips headed to downtown Ottawa are by a transit.
  BTOD photo
Ottawa Busway Photo
TOD Facts $1 Can billion ($US 675 million) in new construction at transitway stations.
Lessons Learned The bus-based Transitway system was the right choice for the Ottawa-Carleton region. It provides a high level of service to the predominantly low-density residences of the region, while also providing a focus for channeling future employment and commercial growth.

Back to top

 

RTOD Case 1
Columbia Pike Streetcar Project (Virginia)

Project Location Arlington and Fairfax Counties, Virginia
RTOD photo
Transit Facilities and Services • Streetcar technology
• Five mile connection between Skyline and Pentagon City
• Six-minute service
• Service augmented with Metro buses during peak periods

RTOD photo
Streetcar Technology

TOD Facts • Include a mixture of community- and neighborhood-serving retail, office, residential, and recreational/cultural uses developed with a pedestrian scale and character.
• New mixed-use projects would create a distinct new identity and provide future access to multi-modal transit options.

Back to top

 

RTOD Case 2
Rosslyn-Ballston Corridor (Arlington County, Virginia)

Project Location Arlington County, Virginia
RTOD photo
Transit Facilities and Services • Five Metro Rail stations in the corridors.
• Transit operator is the Washington Metropolitan Transportation Authority (WMTA).
TOD Facts • Over 21 million square feet of office, retail, and commercial space
• More than 3,000 hotel rooms
• Almost 25,000 residences
  RTOD photo
Corridor Development Patterns

RTOD photo
Rosslyn-Ballston Corridor Photo

Lessons Learned • Think big and involve all stakeholders in dialogue
• Take your time on the big framework decisions. Once the framework is set, stick to it
• Have high expectations
• Plan well
• Be patient
• Maintain integrity of plan
• Be consistent
• Density can motivate the private sector.

Back to top

 

RTOD Case 3
South End TOD (Charlotte, North Carolina)

Project Location Charlotte, North Carolina

RTOD photo

Transit Facilities and Services • Light rail operated by the Charlotte Area Transit System
• Light rail stations in the South End District: Carson Boulevard, Rensselaer Avenue and East Boulevard
TOD Facts • The overall vision for South End is to become a vibrant, historic, pedestrian-oriented urban district focused around a multi-modal transportation corridor that serves pedestrians, bicyclists, bus transit, trolley, light rail, and motorists, and is a community gathering place for Wilmore and Dilworth.

Back to top

 

RTOD Case 4
Mockingbird Station TOD (Dallas, Texas)

Project Location Dallas, Texas

RTOD photo

  RTOD photo
Mockingbird Station Photo
Transit Facilities and Services • Light rail operated by the Dallas Area Rapid Transit
• Mockingbird Station located 4 miles north of downtown Dallas
TOD Facts • Assemblage of offices, shops, restaurants, and lofts near the station cost around $145 million
• Includes 211 upscale loft residences, 140,000 square feet of office space, and 180,000 square feet of destination and convenience retail, theaters, and restaurants

Back to top

 

RTOD Case 5
Englewood CityCenter TOD (Englewood, Colorado)

Project Location Englewood, Colorado
Transit Facilities and Services Light Rail
TOD Facts

RTOD photo

Lessons Learned • Public sector was willing to invest substantial public resources and was focused on the goals of reinvigorating the community and establishing a development with long-term financial viability.
• City made a strategic investment to relocate civic facilities to the CityCenter area, helping to encourage private-sector investment.

Back to top

 

RTOD Case 6
Orenco Station Town Center (Hillsboro, Oregon)

Project Location Hillsboro, Oregon
RTOD photo
Transit Facilities and Services Light Rail operated by Portland Tri-Met
TOD Facts • TOD will encompass 450 to 500 attached town homes and detached homes along with 1,400 luxury apartment units.
• One of the communitys focal points will be a town center that will initially feature 25,000 square feet of retail space, with 22 apartments or lofts above retail establishments and 24 live-work town homes.
• An additional 30,000 square feet of retail space will be available for future development.

Back to top

 

RTOD Case 7
Bethesda Metro Center (Bethesda, Maryland)

Project Location Bethesda, Maryland

RTOD photo

  RTOD photo
Metro Bethesda Station Photo

RTOD photo
Metro Bethesda Station TOD Photo

Transit Facilities and Services Metro rail operated by the Washington Metropolitan Area Transit Authority
TOD Facts • 400,000 square feet of office space
• A 380-room Hyatt Hotel
• 60,000 square feet of retail space
• Aair-rights lease at the Bethesda Station generates $1.6 million annually in rent

Back to top

 

RTOD Case 8
Lindbergh City Center (Atlanta, Georgia)

Project Location 2424 Piedmont Road
Atlanta, GA 30324
RTOD photo
Transit Facilities and Services • This is the second busiest station in the MARTA system, handling an average of 23,400 boardings per weekday.
• Intersection of North-South Line and Northeast-South Line.
• Connections: GRTA, Royal Bus Lines buses.
  RTOD photo
Lindbergh City Center Photo
TOD Facts • 1.3 million square feet of office space, retail shops and a hotel, plus residential condominiums, are slated for an 11-acre park-and-ride lot.
• A pedestrian-friendly Main Street, featuring retail shops and restaurants, will bridge over the rail station into a multifamily residential district.
• One of Atlanta’s largest companies, BellSouth, will be the projects anchor tenant.

Back to top

 

RTOD Case 9
Dadeland North and South (Miami, Florida)

Project Location Miami, Florida

RTOD photo

Transit Facilities and Services • Metro rail operated by Miami-Dade Transit Authority
• Daily ridership = 67,000

RTOD photo
Datran Center Office Towers

TOD Facts • Jjoint development projects at Dadeland North and South currently yield $800,000 in annual lease revenues.
• The agency is currently seeking to enter into deals with private interests to develop 11 agency-owned properties.

Back to top

 

RTOD Case 10
Ohlone-Chynoweth TOD (San Jose, California)

Project Location San Jose, California

RTOD photo

  RTOD photo
Ohlone-Chynoweth Station Photo
Transit Facilities and Services • Light rail operated by Santa Clara Valley Transportation Authority (VTA).
• Ohlone-Chynoweth station is located at the junction of Alum Rock-Santa Teresa Line and Almaden Shuttle.
TOD Facts • 330 units of affordable housing, targeted to people making between 30% and 60% of the area median income
• 40 park-and-ride spaces
Project Financing Total project cost of $31.6 million.
• $14.5 million in tax-exempt bonds
• $10.5 million in tax credit equity
• $5.2 million loan from the City to support affordable housing
• $824,000 in federal transportation funds for improvements
• $500,000 Affordable Housing grant
• $350,000 State Proposition 1 funds to reimburse the school fee

Back to top

 

RTOD Case 11
The Tide – Norfolk’s Future Light Rail Transit System (Norfolk, Virginia)

Project Location Norfolk, Virginia
RTOD photo
Transit Facilities and Services • $232 million project
• Extends 7.4 miles from the Eastern Virginia Medical Center through downtown Norfolk, and continues along the Norfolk Southern Right of Way, adjacent to the I-264 corridor to Newtown Road
• 11 stations
• Project sponsor is Hampton Roads Transit (HRT), the region’s sole transit provider
Project Status • Construction is under way
• Operational by 2010

Back to top